Location: Burkina Faso
Rabotec Group, in partnership with Outotec, was contracted for the installation of a Ball Mill and a SAG Mill at the Bissa Gold Project in Burkina Faso, managed by Lycopodium Minerals. Rabotec provided a skilled installation crew and specialized tools, working under Outotec’s supervision to complete the mechanical installation.
In addition to the mechanical work, Rabotec handled all electrical installations and supported the commissioning process, ensuring the systems were fully operational. The project was delivered on schedule, meeting high standards of safety and quality, and reinforcing Rabotec’s reputation in the mining sector.